BMS Sierra
BRISTOL MYERS SQUIBB - SIERRA
SAN DIEGO, CA
Value Provided
GMC Commissioning's technical value was brought to the project through in-depth expertise. Our ability to communicate effectively, appropriately address relevant issues, and provide creative troubleshooting suggestions allowed the project to stay on budget and schedule.
Project Overview
This project is a large tenant improvement buildout of roughly 420,000 SF that will consolidate many of the BMS San Diego science business units into a single building.
GMC Cx provided whole-building, technical commissioning services for the new 7 level, 420,000 SF, $330+ million building including all MEP and building automation system components. GMC Cx was brought on early for a design assist role and worked with the teams on design phase reviews, acceptance criteria and owner requirements. GMC Cx Provided a custom-built fault detection and performance analytics system using Skyspark.
Included in the scope was monitoring of Central Utility Plant provided under the core and shell scope with SkySpark.
Systems Commissioned
Mechanical Systems including AHU, CRAC, and CAVs
Electrical, Emergency Power, Lighting Controls
Plumbing Systems including Compressed Dry Air, RODI, Domestic Hot and Cold Water
Lab Exhaust
Fume Hoods and Specialty Equipment
Solvent Delivery and Waste
Cold Rooms, Freezer Rooms, Vivarium
Sound Level and Vibration Testing
Safety, Gas Detection, Fire Protection and Suppression
Security System and AV Cabling
Landscape Irrigation Controls
Building Automation System