GMC Commissioning's technical value was brought to the project through in-depth expertise.  Our ability to communicate effectively, appropriately address relevant issues, and provide creative troubleshooting suggestions allowed the project to stay on budget and schedule.

Project Overview

The 210 Adrian Project, owned by Millbrae Adrian Science Park LLC (an affiliate of Longfellow Real Estate Partners), is transforming a former self-storage facility into a state-of-the-art lab and office building targeting LEED Gold and Fitwel certifications. Designed by Flad Architects, the development includes a rooftop terrace, fitness center, and public café. GMC Cx provided comprehensive commissioning for all MEP and control systems, performing 100% performance testing and leveraging Facility Grid for real-time documentation. Monitoring-Based Commissioning (MBCx) was implemented to optimize efficiency and reliability, supporting the project’s sustainability goals and alignment with LEED Gold standards.

 

Systems Commissioned

  • Mechanical Systems including AHU, CAVs and VAVs​

  • Electrical, Emergency Power, Lighting Controls, Photovoltaic Arrays

  • Plumbing Systems including Compressed Dry Air, Domestic Hot and Cold Water, Sewage Controls

  • Lab Exhaust

  • Building Automation System

  • Building Envelope System