When "Done" Doesn't Mean Ready: The Real Work of Commissioning
- Alex Mathers
- 2 days ago
- 4 min read
Alex Mathers P.E., CxA, NEBB CP
Most people think commissioning is about testing systems. After 20 years in the field, I can tell you it's mostly about something else entirely. It's about working between contractors, vendors, and customers to make sure what's "done" is actually complete and ready to be tested.
That gap between "done" and "ready" is where commissioning lives or dies.
The Project Schedule Game
Every project I've worked on has a schedule that is very detailed in the beginning. Demo, framing, drywall, and rough-ins are very detailed, however once it gets to TAB, startup, and testing there is usually one line item that says “commissioning” and starts on a specific date. The problem is, schedules don't know what's happening in the field. They don’t know delays, lead times, issues, troubleshooting, repairs, and required fixes and replacement. Schedules show what should be happening, not what is happening.
Readiness isn't a date on a schedule. It's a condition. A site visit tells the true condition of the space. If you aren't prepared, you can walk in expecting to start testing, but you'll find filters not installed, TAB not complete, actuators needing replacement, and a BAS that drops offline every few hours. The schedule said ready. Reality said otherwise.

Meetings vs. The Field
What gets discussed in coordination meetings is not always what is happening in the field. You’re shocked, I know.
In meetings, everyone reports progress. Mechanical is 95% complete. Controls programming is loaded. TAB is wrapping up next week. Everyone nods, the schedule gets updated, and the meeting ends.
Then you walk the site. The 95% mechanical complete actually means three air handlers haven't been started. "Controls programming loaded" means the logic is in the controllers but nobody has verified it against the approved sequences. TAB wrapping up means they are waiting for ceiling tiles and doors to be installed.
This isn't anyone lying. It's how construction reporting works. Optimism rolls uphill, and problems get smoothed over. CxA's job is to cut through that polish and report what's actually true.

Clear Ownership Matters
Most testing failures don't happen because people don't know what to do. They happen because nobody knows whose job it is. When ownership is fuzzy, things fall through the cracks. When two trades both think it's the other's responsibility, nothing gets done. When everyone owns it, nobody owns it.
Clear ownership between teams makes or breaks execution. The CxA often ends up being the person who forces those conversations. Not in a confrontational way, but with the simple question, "Who's doing this and when?"
The Checklist Solves a Specific Problem
We developed a "Functional Testing Site Readiness Checklist" to address all three of these issues at once. It's not paperwork for the sake of paperwork. It's a tool that does three specific jobs.
It defines what "ready" actually means. Instead of vague status updates, the checklist lists specific conditions that must be true: Permanent power stable; Sensors calibrated; All systems in auto with no overrides active. There's no room for interpretation.
It forces field verification. A contractor can't honestly check the box that says "all control loops verified and tuned" without actually doing the work. The checklist creates a moment where field reality has to match the report.
It assigns ownership. Each item belongs to a specific trade. The electrical contractor handles their items. Controls handles theirs. The checklist becomes a coordination tool that makes ownership visible.
Here is our developed Readiness Checklist:
Functional Testing Site Readiness Checklist
General Notes
Complete and permanent identification/labeling of all systems and components
Pre-functional checklists and pre-testing complete
Clear, safe access to all equipment
Pencils down, hands-off readiness: 48 hours of continuous automatic operation with no manual intervention, overrides, or alarms
Electrical & Lighting Systems
Permanent power stable and panels complete
Electrical acceptance testing complete
Motor starters and overloads set and tested
Lighting controls and emergency lighting complete
Mechanical Systems
Equipment startup and manufacturer reports complete
VFDs programmed and locally tested
Final filters and strainers installed
Dampers and actuators stroked full travel
Plumbing & Hydronic Systems
Domestic and process water supplies connected and tested
Hydronic systems flushed, filled, and balanced
DHW/IHW circulation and temperature verified
Test and Balance
TAB substantially complete with report submitted
Ventilation rates verified at design conditions
Controls & Automation
Field devices installed with point-to-point checkout complete
Sensors calibrated to design values
Control loop checks complete
Graphics and programming loaded and verified
BAS network stable with integration complete
SkySpark integration complete
All systems in auto with no overrides or bypasses active
Safety Systems
All equipment safeties tested
All life-safety interlocks tested
AHJ Sign-offs
Final electrical inspection signed off by AHJ
Final mechanical inspection signed off by AHJ
Fire alarm testing complete and signed off by AHJ
Fire sprinkler/suppression testing complete and signed off by AHJ
What I've Learned
A site can look ready. Equipment is installed. Lights are on. Air is moving. People are working. But looks are deceiving. When the details are right, functional testing goes smoothly. When they're not, you spend your testing time troubleshooting installation problems instead of verifying performance. That's expensive for everyone.

The Bottom Line
The CxA role isn't glamorous. A lot of it is asking uncomfortable questions. It's prioritizing real-world constraints over schedule optimism. It's filling in the gaps and getting alignment when things don't line up as cleanly as the project manager hoped.
A good readiness checklist makes that work easier. It gives everyone a shared definition of done. It creates accountability without requiring confrontation. And it shifts the conversation from "Are we ready?" to "What specifically isn't ready and who's fixing it?"
That's a much more useful conversation. And it's the only way to start functional testing without wasting everyone's time.
References and Further Reading:
ASHRAE Guideline 0. The Commissioning Process. American Society of Heating, Refrigerating and Air-Conditioning Engineers.
ASHRAE Guideline 1.1. HVAC&R Technical Requirements for the Commissioning Process.
ANSI/NEBB Standard S110-2019
BCxA Best Practices documents
ASHRAE Guideline 36 (sequences of operation)
NFPA 72 (fire alarm)
NETA ATS (electrical acceptance testing)
AABC or NEBB TAB Standards
ASHRAE Standard 188 (Legionella/water systems)
